Hunt Club Road & Washington Intersection
General Information
- Start Date: Fall 2024
- Est. Completion Date: Fall 2026
- Location: Intersection of Hunt Club Road and Washington Street
- Project Cost: $16.3 million
- Contractor: Ciorba Group
- Project Impacts:
- Traffic delays
- Lane closures
Project Description
LCDOT will be expanding the intersection at Hunt Club Rd. and Washington St. They will be adding dedicated left and right turn lanes for all four legs of the intersection as well as installing a pedestrian path that will tie the existing Washington St. path to the Village’s path, north to Dada Dr. There will be traffic delays and lane closures.
Project Updates
Visit LCDOT's website for detailed information.
Update May 27, 2026: The contractor will continue to work on the installation of the center medians along Washington Street and the permanent traffic signal lights.