Street Resurfacing Program
General Information
- Start Date: May 2023
- Est. Completion Date: October 2023
- Location: (See List Below)
- Project Cost: $4.5 million
- Contractor: J.A. Johnson Paving
- Project Impacts:
- Narrow lanes and lane closures
- Sidewalk closures
- Temporary driveway access closures
Project Description
The Village's contractor, J.A. Johnson Paving, will be resurfacing 6 miles of roadway as well as completing pavement patching and curb and sidewalk repairs. The following streets are planned to be resurfaced this year:
Locations & Description of Work
- Zone 1 Map (PDF): Nursery Dr--Knowles Rd to east end; Greystone Dr--North cul-de-sac to Scranton Dr; Sutton Pl--Nursery Dr to west end; Sawyer Ct--Greystone Dr to south end; Suffolk Ct--Hartford Dr to west end; Prescott Ln--Cascade Way to west cul-de-sac; Old Walnut Cir--Cascade Way to Washington St; Cascade Way--Kingsport Dr to Old Walnut Cir; Abbey Rd--Strawberry Fields to Aster Dr; Strawberry Fields--North end to Cascade Way; Aster Dr--Bittersweet Dr to Cascade Way; Penny Ln--Aster Rd to Cascade Way
- Zone 2 Map (PDF): Delaware Ave--Lawson Blvd to east end; Sycamore Ln--Pinewood Rd to south end; Acacia Ct--Lawson Blvd to west end; Hollyhock Ct--Lawson Blvd to west end; Alder Ct--Lawson Blvd to west end; Adele Dr--Route 21 to north end; Yew Ct--Pinewood Rd to north end; Monterey Ct--Pinewood Rd to north end; Acorn Ct--Pinewood Rd to west end
- Zone 3 Map (PDF): Waveland Ave--Grand Ave to Grandmore Ave; Grandville Ave--Railroad to Magnolia Ave; Woodlawn Ave--Waveland Ave to Pine Grove Ave; Magnolia Ave--Woodlawn Ave to north end; Harper Ave--First Ave to east end
- Zone 4 Map (PDF): Covenant Ct--Kings Way to south end; Concord Sq--Kings Way N o Kings Way N; Lexington Sq--Providence Rd to Providence Rd; Spinney Run Dr--Rte 21 to Kristin Ct; Brian Ct--Spinney Run Dr to south end; Chelsey Ct--Spinney Run Dr to north end; Kristin Ct--Spinney Run Dr to west end
Project Updates
October 6, 2023: The Village's contractor, J.A. Johnson Paving, has finished the roads in this year’s resurfacing program and will continue patching at various locations throughout the Village.
September 29, 2023: The Village's contractor, J.A. Johnson Paving, has finished up all roads in this year’s resurfacing program and will continue patching at various locations throughout town.
September 22, 2023: The Village's contractor, J.A. Johnson Paving, has finished up all roads in this year’s resurfacing program and will continue patching at various locations throughout town.
September 15, 2023: The Village's contractor, J.A. Johnson Paving, has finished up the final restoration and will continue to patch at various location throughout town next week.
September 8, 2023: The Village's contractor, J.A. Johnson Paving, has completed all the roads in this year's resurfacing program and will complete the final restoration of Area 3 next week.
September 1, 2023: The Village's contractor, J.A. Johnson Paving, will begin patching throughout town over the next four weeks.
August 25, 2023: The Village's contractor, J.A. Johnson Paving, will begin patching throughout town over the next four weeks.
August 4, 2023: The Village's contractor, J.A. Johnson Paving, will begin resurfacing in Area 3 next week. The Cunningham Court Bridge has been poured and will be curing this next week and will reopen the following week. Restoration will continue in all areas and signage will be picked up as the areas are completed.
July 28, 2023: The Village's contractor, J.A. Johnson Paving, is anticipating to fully surface zones 1, 2, & 4 by next week. The contractor will begin milling and under cutting in Zone 3 this week. The westbound lane of the Cunningham Ct. bridge will be poured next week.
July 21, 2023: The Village's contractor, J.A. Johnson Paving, has completed Area 1's surface and Area 2 will be completed by early next week. Driveways are being repaired throughout the construction zones. Milling, undercuts, and patching will begin in Area 3 and 4 this week.
July 14, 2023: The Village's contractor, J.A. Johnson Paving, will fully surface Zone 1 by early next week. The contractor will begin milling in Zone 4 next week as well. Delaware Ave. will receive leveling binder next and the cul-de-sacs of Zone 2 will receive final surface. The eastbound lane of the Cunningham Ct. bridge will be poured next week.
July 7, 2023: The Village's contractor, J.A. Johnson Paving, will be place the final surface in area 1 early next week. Milling and patching operations will be moving to areas 2 through 4. The contractor will continue to repair driveways damaged by curb and sidewalk work.
June 30, 2023: The Village's contractor, J.A. Johnson Paving, has completed milling and patching operations on the east side of Gurnee. Those operations will soon move into the Kensington area. The contractor will continue to repair driveways damaged by curb and sidewalk work. The contractor will complete the final surface for the east side of Gurnee and the Kensington Area before moving to the Westgate and Pembrook subdivisions. The final surface should be completed within the next two weeks.
June 23, 2023: The Village's contractor, J.A. Johnson Paving, has most of the binder down on the east side of Gurnee. Driveways are being repaired throughout the construction zones. Undercut and patching work will continue on the east side of the Village.
June 16, 2023: The Village's contractor, J.A. Johnson Paving, will continue milling operations next week. Subgrade improvements will occur for the roads that were milled down to stone. The removal and replacement of damaged culverts are scheduled for applicable roads next week. The contractor also plans to complete patching and subsequent paving on roads that have been milled.
June 9, 2023: The Village's contractor, J.A. Johnson Paving, has begun milling operations on various streets in this year's resurfacing program and will continue in the coming weeks. The contractor has begun repairing driveways damaged by curb and sidewalk work. The final surface will be placed on Nursery, Greystone, Sutton, and Sawyer next week. Streets that have been milled will receive their first layer of asphalt next week. The removal and replacement of damaged culverts for the streets on the east side of Gurnee will begin next week.
June 2, 2023: The Village's contractor, J.A. Johnson Paving, will finish curb and sidewalk repairs by next week and residents will have full driveway access at that time. Also, milling and patching operations will begin next week in area 1 on the east side of the Village. Residents should refrain from parking on the street during working hours.