Dilleys Road Pedestrian Path
General Information
- Start Date: April 2024
- Est. Completion Date: August 2024
- Location: East side of Dilley's Rd. from Stearns School Rd. to the ComEd pedestrian path near the Pembrook Water Tower
- Project Cost: TBD
- Contractor: TBD
- Project Impacts: Temporary lane and sidewalk closures
Project Description
The Village will install an 8 ft. wide pedestrian path along the east side of Dilley's Rd. from Stearns School Rd. to the ComEd pedestrian path near the Pembrook Water Tower.
Project Updates
July 31, 2024: The Village's contractor, Everlast Blacktop, has completed restoration on Dilleys Road.
July 5, 2024: The Village's contractor, Everlast Blacktop, has completed the pedestrian path along Dilleys Rd. Restoration work will begin the week of July 8th, weather depending.